Client
Allianz Arena
Project duration
2013 – 2014
Calm before the storm
Requirements
Over several months in 2013 and 2014 the underground train line to the Allianz Arena was out of operation due to construction works. The Allianz Arena is generally occupied for the FC Bayern games with over 70,000 spectators, of these up to 30,000 use public transport. This was considered the safest and most reliable way to get to the game and home again.
Implementation
This particular challenge was solved with shuttle buses. Up to a hundred buses from Autobus Oberbayern and the MVG stood at the ready to offer a smooth and continuous service.
You can download here a best practice presentation we held on the topic in November 2014 at the IBIT-Fachtagung – conference on event safety (only available in German).
Our services
- Transportation and safety concept
- Coordination with the local authorities
- Organisation and coordination
- Continuous Improvement
More on Mobility
Contact & Imprint
Companeer GmbH
Parkstr. 22 | 80339 Munich
Phone +49 (89) 21 55 10 31
hello@companeer.com
© 2025 Companeer GmbH
Managing director:
Thomas Albinger
Commercial register:
Munich HRB 202961